Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Latest CORE Questions

Page: 14 / 23
Total 312 questions

Supply Management Core Exam Questions and Answers

Question 53

During negotiations, each side adopts a point of view, and then both parties work to close the gap by exchanging concessions. Which of the following tactics is being used?

Options:

A.

Positional bargaining

B.

Logical reasoning

C.

Power and influence

D.

Relational persuasion

Question 54

CDE, Inc. contracts with a supplier for the fabrication of trade show booths and displays. The contract is on a cost-plus fixed fee (CPFF) basis, with the supplier's agreed-upon fee set at $15,000

and the estimated allowable cost of materials set at $20,000, for a total of $35,000. The supplier is able to bring down total material costs to $18,500. Given this situation, how much can the

supplier bill CDE for the project?

Options:

A.

It will depend upon the profit margin allowed by the contract

B.

$35,000

C.

$33,500

D.

Up to $35,000, based on CDE's acceptance of components

Question 55

A supply manager Is conducting negotiations with a supplier. The supplier states that it cannot offer a lower price because the product under negotiation is covered by a government contract. In this situation, the supply manager should

Options:

A.

offer to reduce the order quantity

B.

negotiate the other terms and conditions, and return to the issue of price at a later time

C.

conclude that this is in fact the best price that the supplier can legally offer

D.

require the supplier to provide specifics on the government contract restrictions

Question 56

A local utility's supply manager is preparing a solicitation to select a contractor to construct a controlling station for the utility's main plant. Construction must begin within four months and be completed in a year or less, as delays in bringing the new station online could cause serious losses for the utility. Which of the following will be MOST effective in monitoring performance and ensuring timely completion?

Options:

A.

Specifying high consequential damages for failure to complete the project in a timely manner

B.

Ensuring that the scope of work is clear, to minimize misunderstandings

C.

Requiring milestones, progress reports, and liquidated damages for noncompliance

D.

Including a strong for-cause termination clause

Page: 14 / 23
Total 312 questions