Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Online CORE Questions Video

Page: 12 / 23
Total 312 questions

Supply Management Core Exam Questions and Answers

Question 45

DEF Inc. receives several batches of inferior quality products from a supplier. Although all of the samples provided by this supplier met or exceeded specifications, it is learned that the facility used to produce the samples is in a different location than the regular production facility, and that the production environment could affect quality.

DEF could have prevented this situation by doing which of the following?

Options:

A.

Requesting and testing samples from all possible supplier manufacturing locations

B.

Requesting larger samples from the supplier prior to going into production

C.

Requiring the supplier to provide assurance that its products will meet the required specifications

D.

Placing stricter quality controls in the receiving dock to prevent defective products from being accepted into inventory

Question 46

A luxury scarf manufacturer located in Europe selects a fine wool supplier in Australia. The manufacturer's supply manager wants to ensure timely monthly deliveries while keeping transportation costs reasonable. Which of the following actions by the supply manager is MOST likely to meet the scarf company's needs?

Options:

A.

Utilize a freight forwarder to schedule and track shipments

B.

Select a consistent Incoterms ® 2020 rule for all shipments

C.

Require the freight carriers to provide real-time tracking

D.

Include a routing guide within the service level agreement

Question 47

The procurement officer for a publicly-traded U.S. company completes a 409 filing with the Securities and Exchange Commission (SEC), due to a number of supplier deliveries being missed that impact revenue forecasts. The procurement officer's NEXT step should be to

Options:

A.

review with the legal department what actions can be taken against suppliers with late deliveries

B.

document a corrective action plan

C.

determine what changes can be made to contracts to ensure suppliers meet delivery deadlines

D.

terminate contracts with suppliers who have been late with deliveries

Question 48

Which of the following is the PRIMARY reason an organization's executive team and internal stakeholders should be aligned on the definitions of cost savings reporting?

Options:

A.

To ensure financial professionals can audit the cost savings reporting process

B.

To ensure price baselines can be adjusted for comparison purposes overtime

C.

To ensure appropriate risk management strategies are being adopted

D.

To ensure supply management is adding value

Page: 12 / 23
Total 312 questions