Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CPSM CORE Exam Dumps

Page: 13 / 23
Total 312 questions

Supply Management Core Exam Questions and Answers

Question 49

A supply manager works with engineering on an aerospace project. A request for quotation (RFQ) Is distributed to five potential suppliers, three of whom respond that they are not interested In the project. The two remaining suppliers say they are interested, but a high level of risk involving tight tolerances will force them to raise prices significantly, and neither will accept a firm fixed price contract. The supply manager arranges a conference with engineering and both suppliers. During this conference, it is determined that only three of the tolerances are truly critical. Based on this conference, a revised RFQ is issued.

This scenario is an example of which of the following aspects of supply management?

Options:

A.

Acting as a liaison between stakeholders

B.

Negotiating a contract award

C.

Facilitating value engineering

D.

Resolving conflicts between stakeholders

Question 50

A supply manager is preparing the department's budget for the next year. Which of the following is the FIRST step in this process?

Options:

A.

Controlling expenditures during the budgetary year

B.

Reviewing the organization's goals

C.

Defining the needed resources

D.

Presenting the budget for review

Question 51

A supply manager seeks bids on a new piece of capital equipment. The equipment is budgeted at $115,000. Three suppliers send in bids of $110,000, $114,000 and 5135,000. After receiving the bids, additional negotiations with the low bidder result in a final cost of $105,000. In this situation, what should the baseline value be for calculating cost avoidance?

Options:

A.

$114,000

B.

$135,000

C.

$110,000

D.

$115,000

Question 52

A U.S.-based supply manager wants to reduce the number of defective parts arriving from an outsourced supplier located in Malaysia. Which of the following is MOST likely to help achieve this goal?

Options:

A.

COPC 2000

B.

Six Sigma

C.

Sarbanes-Oxley

D.

Lean manufacturing

Page: 13 / 23
Total 312 questions