Supply Management Core Exam Questions and Answers

Question 41

One of TUV Company's largest suppliers has been performing poorly, and the quality of its services does not meet the needs of a particular stakeholder. Which of the following is the BEST way for TUV's supply manager to evaluate how to establish service level agreements (SLAs) to improve the performance of this supplier?

Options:

A.

Request that the supplier provide a set of metrics to be used in measuring performance

B.

Develop measurements of supplier performance with the stakeholder, and include those measurements in an amendment to the contract

C.

Notify the supplier that its level of performance is not acceptable, and renegotiate contract pricing to reflect the supplier's performance

D.

Notify the supplier of the performance issues, and terminate the contract if the supplier does not correct performance within thirty days

Question 42

A supplier's willingness to deal with rejected materials, fill surges in orders, and provide technical support will be MOST affected by which of the following?

Options:

A.

Creating teaming agreements with suppliers

B.

Negotiating Inclusive terms and conditions

C.

Maintaining good supplier relationships

D.

Including such conditions in the statement of work

Question 43

DEF, Inc. is a multinational oil company expanding into a new geographic region. The firm's policy is to purchase locally for its operations whenever possible. Thus, DEF needs to find sources of materials, basic equipment, and standard bulk items within the new region. Which of the following should DEF do FIRST?

Options:

A.

Issue a Request for Quotation (RFQ)

B.

Conduct a suppliers' conference

C.

Issue a Request for Information (RFI)

D.

Issue a Request for Proposal (RFP)

Question 44

An automobile manufacturer learns that its supplier for brake parts cannot maintain a steady workforce of machinists. In this instance, it is likely that the manufacturer failed to examine which of the following during supplier performance evaluations?

Options:

A.

Labor stability

B.

Quality metrics

C.

Financial stability

D.

Business continuity