Question 69

During the construction phase of a project you are managing, the customer wishes to add to the project scope. You think that the cost of the change is 25% greater than your contingency. What steps will you take?

Options:

A.

Get an estimate from the contractor for a change order. Also, review the impact this will have on the entire project’s cost, schedule, quality, and risks. Present these findings to the customer along with the request for additional funds.

B.

Tell the customer you may be able to accommodate their request if the contingency budget is not used for other issues. Try to cut other scope items or create savings in other parts of the project to fully fund this request.

C.

Tell the customer that their request is out of scope and cannot be accommodated. The project does not have the funds for this additional work. Explain how this request impacts schedules delaying work and adding significantly to time as well as cost.

D.

Immediately agree to add the work to your project scope without getting an estimate from the contractor to determine the additional cost. You and the contractor can work out the differences as you go along.

Question 70

You were tasked with preparing the Service Level Agreement and Key Performance Indicators for a contract. What key characteristics should you consider when writing the Key Performance Indicators (KPIs)?

Options:

A.

The KPIs must be tied to the budget.

B.

The KPIs must be easily attainable.

C.

The KPIs must measure all outcomes equally.

D.

The KPIs must be clear and understandable.

Question 71

An organization recently acquired another firm with an 88-acre campus and fourteen buildings that support government-regulated activities. The Chief Financial Officer has asked the facility manager to provide an assessment of the property and facilities. One of the assessments the facility manager will perform is the Facility Condition Index (FCI). Which has the GREATEST impact on the FCI?

Options:

A.

Utility distribution.

B.

Real estate value.

C.

Building openings.

D.

Deferred maintenance costs.

Question 72

Part of your goals is to develop a succession plan for key positions within your operation, including yourself. What is most helpful in reaching this goal?

Options:

A.

Conduct staff interviews to see who wants to be promoted.

B.

Conduct a review of staff goals and objectives.

C.

Conduct a skills gap analysis of current staff and incorporate the results into training goals.