The process of developing a detailed description of the project and product is known as:
Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
A weighting system is a tool for which area of procurement?
Which of the following is an example of push communication?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
The definition of operations is a/an:
What’s budget?
Which tool or technique is used to develop the human resource management plan?
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Which of the following is the correct network diagram for the table?
Which of the following is an output of the Perform Integrated Change Control process?
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Another name for an Ishikawa diagram is:
Who is responsible for developing the project management plan and all related component plans?
Which of the following is an output of the Conduct Procurements process?
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?
The Perform Quality Assurance process occurs in which Process Group?
Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?
Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?
To which process is work performance information an input?
Team performance assessments is an output of which of the following processes?
A process is defined as:
Which of the following can be used as an input for Define Scope?
Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500 PV= $750 AC= $1000 BAC= $1200
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
An output of Control Schedule is:
Which output is the approved version of the time-phased project budget?
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
Which of the following is an output of the Monitor and Control Project Work process?
Reserve analysis is a tool and technique used in which process?
Change requests are processed for review and disposition according to which process?
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Which tool or technique is used in the Perform Integrated Change Control process?
The chart below is an example of a:
An input to the Plan Procurement Management process is:
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
Which of the following tools and techniques is used to estimate cost?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
Which technique helps to determine the risks that have the most potential impact on a project?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
An associate who calculates fees daily to support the department is doing which of the following?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
The Perform Integrated Change Control process occurs in which Process Group?
Which technique is utilized in the Schedule Control process?
A tool or technique used during the Administer Procurements process is:
An input to the Perform Quantitative Risk Analysis process is the:
Which technique is utilized in the Control Schedule process?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which activity may occur at project or phase closure?
At the end of the project, what will be the value of SV?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
Which of the following is a tool or technique of the Define Activities process?
When are deliverables accepted or not accepted?
When is a project finished?
Which organizational process assets update is performed during the Close Procurements process?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
The individual or group that provides resources and support for a project and is accountable for success is the:
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
When sequencing activities, what does the common acronym FF stand for?
Which of the following is an output of Close Procurements?
The process for performing variance analysis may vary, depending on:
A reward can only be effective if it is:
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
What type of reward can hurt team cohesiveness?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Which of the following choices is a contract closure tool or technique?
Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
Which action should a project manager take to ensure that the project management plan is effective and current?
Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
One of the key benefits of the Plan Human Resource Management process is that it:
Organizational theory is a tool used in which Project Human Resource Management process?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
The progressive detailing of the project management plan is called:
Create WBS is part of which of the following Knowledge Areas?
During what process is the quality policy determined?
Which of the following is a group decision-making technique?
The organizational process assets that are of particular importance to Plan Communications are:
The milestone list is an input to which process from the Planning Process Group?
What is an objective of the Develop Project Team process?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Which of the following are outputs of Develop Project Team?
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Which of the following inputs is required for the WBS creation?
Which is used to solicit proposals from prospective sellers?
Stakeholder communication requirements should be included as a component of:
What are the identified risks for doing excessive decomposition in a WBS?
The lowest level normally depicted in a work breakdown structure (WBS) is called a/an:
Progressively elaborating high-level information into detailed plans is performed by the:
The scope management plan and scope baseline are contained in:
Which tool or technique is used in the Plan Scope Management process?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Inputs to Identifying Stakeholders include:
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
Which type of analysis is used as a general management technique within the Plan Procurements process?
A weighting system is a tool for which area of Conduct Procurements?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Prototype development may be used as a tool for which of the following risk response strategies?
Through whom do project managers accomplish work?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
Which statement correctly describes the value of a business case?
The process of defining how the project scope will be validated and controlled is known as:
In which process is a project manager identified and given the authority to apply resources to project activities?
Which of the following is an input to the Qualitative Risk Analysis process?
A tool and technique used in the Develop Project Charter process is:
Which of the following response strategies are appropriate for negative risks or threats?
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
What are the components of the “triple constraint”?
One of the objectives of a quality audit is to:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
High-level project risks are included in which document?
Plan Risk Management is the process of defining how to:
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
The purpose of developing a project scope management plan is to:
Identify Risks is part of which Process Group?