Question 45

Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

Options:

A.

Analogous Estimating

B.

Expert Judgment

C.

Optimistic Estimates

D.

Reserve Analysis

Question 46

Which of the following tools and techniques is used to estimate cost?

Options:

A.

Budget forecast

B.

Variance analysis

C.

Activity cost estimate

D.

Three-point estimate

Question 47

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

Options:

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Question 48

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis