New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF PMI-001 Study Guide

Page: 20 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 77

A reward can only be effective if it is:

Options:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Question 78

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Question 79

What type of reward can hurt team cohesiveness?

Options:

A.

Sole-sum

B.

Win-lose

C.

Lose-win

D.

Partial-sum

Question 80

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Options:

A.

Negative

B.

Zero

C.

Positive

D.

Free

Page: 20 / 34
Total 918 questions