New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Pass PMI-001 Exam Guide

Page: 10 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 37

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Question 38

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Question 39

The chart below is an example of a:

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Question 40

An input to the Plan Procurement Management process is:

Options:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Page: 10 / 34
Total 918 questions