Question 33

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Question 34

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Question 35

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Question 36

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Page: 9 / 34