New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMI-001 Questions Answers

Page: 18 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 69

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result

B.

Product

C.

Service

D.

Improvement

Question 70

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

Options:

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

Question 71

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Question 72

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

Options:

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Page: 18 / 34
Total 918 questions