Question 61

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Question 62

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question 63

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Question 64

When are deliverables accepted or not accepted?

Options:

A.

When the project is initiated

B.

As an output of the scope verification process

C.

When the project is closing

D.

In the contract closure process