New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Newly Released PMI PMI-001 Exam PDF

Page: 23 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 89

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

Options:

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Question 90

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Question 91

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Question 92

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Page: 23 / 34
Total 918 questions