PMI-SP Premium Exam Questions

Page: 9 / 12
Total 323 questions

PMI Scheduling Professional Questions and Answers

Question 33

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Options:

A.

Scope Verification

B.

Configuration Management System

C.

Project Management Information System

D.

Integrated Change Control

Question 34

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

Options:

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

Question 35

The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Options:

A.

Activity list

B.

Milestone list

C.

Activity attributes

D.

Project document updates

Question 36

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

Options:

A.

$176,675

B.

$122,845

C.

-$85,000

D.

-$51,000