New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI-SP Exam Dumps : PMI Scheduling Professional

PDF
PMI-SP pdf
 Real Exam Questions and Answer
 Last Update: Dec 21, 2024
 Question and Answers: 323
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
PMI-SP exam
PDF + Testing Engine
PMI-SP PDF + engine
 Both PDF & Practice Software
 Last Update: Dec 21, 2024
 Question and Answers: 323
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
PMI-SP Engine
 Desktop Based Application
 Last Update: Dec 21, 2024
 Question and Answers: 323
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

PMI Scheduling Professional Questions and Answers

Question 1

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Buy Now
Question 2

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

Options:

A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

Question 3

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Options:

A.

Four days

B.

Six days

C.

Five days

D.

Zero, it is on the critical path.