Helping Hand Questions for PMI-SP

Page: 2 / 12
Total 323 questions

PMI Scheduling Professional Questions and Answers

Question 5

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options:

A.

Resource competition

B.

Matrix organization

C.

Resource requirement

D.

Resource constraint

Question 6

What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?

Options:

A.

($450,000 - $180,000) / ($450,000 - $191,000)

B.

$450,000 - $477,500

C.

$180,000 / $247,500

D.

$180,000 - $247,500

Question 7

You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?

Options:

A.

Organizational process asset

B.

Scheduling tool

C.

Project Management Information System

D.

Project office software

Question 8

Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?

Options:

A.

Constructability Analysis process

B.

Schedule Maintenance process

C.

Schedule Development process

D.

Perform Integrated Change Control process

Page: 2 / 12
Total 323 questions