Download Latest PMI-SP Questions

Page: 3 / 12
Total 323 questions

PMI Scheduling Professional Questions and Answers

Question 9

You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?

Options:

A.

Nothing, the 45 hours limit is a guideline.

B.

The project will take longer to complete.

C.

The project will take less time to complete.

D.

The project will require more resources.

Question 10

Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process? Each correct answer represents a part of the solution. Choose all that apply.

Options:

A.

Internal and External

B.

Vertical and Horizontal

C.

Confronting and problem solving

D.

Formal and Informal

Question 11

You are the project manager for the GHB Organization. Management has asked that you review your recent SPI to determine why there was a schedule variance. They'd also like you to explain what approach you'll do to counteract the SPI going forward in the project. You complete the variance analysis and report to management that you'll be fast tracking a portion of your project work. What will be the management's concern with, when it comes to fast tracking the project?

Options:

A.

Added costs for the additional project labor

B.

Added risk

C.

Continued variances in the SPI

D.

Slippage in the project quality

Question 12

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

Options:

A.

Project Schedule Management Plan

B.

Project Staffing Management Plan

C.

Project Human Resources Management Plan

D.

Project Communications Management Plan