What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?
The project manager is looking at a precedence diagram.... the duration of this task?
The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.
What is the outcome of the duration of this task'?
Match the life cycle type to when its requirements are defined.
Which of the following are components of the project management plan?