New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF CAPM Study Guide

Page: 19 / 85
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 73

What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?

Options:

A.

Initiating

B Executing

B.

Monitoring and Controlling

C.

Planning

Question 74

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task'?

Options:

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Question 75

Match the life cycle type to when its requirements are defined.

Options:

Question 76

Which of the following are components of the project management plan?

Options:

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

Page: 19 / 85
Total 1135 questions