New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM Changed CAPM Questions

Page: 50 / 85
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 197

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Question 198

Organizations perceive risks as:

Options:

A.

events that will inevitably impact project and organizational objectives.

B.

the effect of uncertainty on their project and organizational objectives.

C.

events which could have a negative impact on project and organizational objectives.

D.

the negative impact of undesired events on their project and organizational objectives.

Question 199

Change requests are an output from which Project Integration Management process?

Options:

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Question 200

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Page: 50 / 85
Total 1135 questions