Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Full Version CAPM PMI Exam

Page: 48 / 99
Total 1326 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 189

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)

Options:

A.

Many expected simple scope change requests

B.

Few expected simple scope change requests

C.

Routine and repetitive activities

D.

Collocated project teams

E.

Use of established templates

Question 190

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Question 191

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Question 192

The component of the risk management plan that documents how risk activities will be recorded is called:

Options:

A.

tracking

B.

scoping

C.

timing

D.

defining

Page: 48 / 99
Total 1326 questions