CAPM Exam Results

Page: 45 / 85
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 177

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Question 178

Which of the following is an example of facit knowledge?

Options:

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Question 179

Creating the project scope statement is part of which process?

Options:

A.

Manage Scope

B.

Collect Requirements

C.

Define Scope

D.

Validate Scope

Question 180

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Page: 45 / 85
Total 1135 questions