Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Full Access PMI CAPM Tutorials

Page: 44 / 98
Total 1305 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 173

Which tool should a project manager use to calculate cost variance for a project?

Options:

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Question 174

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Options:

A.

Identify the crashed project schedule to find the shortest duration to complete the project.

B.

Identify the longest activity path in the schedule with the shortest possible duration.

C.

Identify the tasks with float duration, which do not impact the duration of the project.

D.

Identify the path through the schedule with leveled resources and the shortest duration.

Question 175

What specific quality considerations should be examined while completing Quality Management plan?

Options:

A.

Risk registerB Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Question 176

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

Options:

A.

5

B.

2

C.

3

D.

4

Page: 44 / 98
Total 1305 questions