New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CAPM CAPM Syllabus Exam Questions Answers

Page: 15 / 85
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 57

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?

Options:

A.

Risk management plan

B.

Communications management plan

C.

Change management plan

D.

Stakeholder engagement plan

Question 58

Which is a major component of an agreement?

Options:

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

Question 59

Which scenario is most desirable during the execution phase of a project?

Options:

A.

Apply and use quality controls to ensure expectations are met throughout the project

B.

Communicate quality failures to the sponsor for feedback

C.

Conduct all quality inspections at the end of the project

D.

Only correct quality issues found if it will keep you within the budget

Question 60

How can a project manager represent a contingency reserve in the schedule?

Options:

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

Page: 15 / 85
Total 1135 questions