Question 109

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Question 110

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Question 111

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Question 112

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities