Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Online ISEB-PM1 Questions Video

Page: 3 / 23
Total 625 questions

BCS Foundation Certificate in IS Project Management Questions and Answers

Question 9

Which of the following would most likely increase the accuracy of estimating the project cost?

Options:

A.

Using historical data.

B.

Pricing out the work at lower levels in the work breakdown structure.

C.

Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects.

D.

Talking to people who have worked on similar projects.

E.

1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects, and 3) Using historical data.

Question 10

The use of group creativity techniques as a tool and technique is done in which of the following processes?

Options:

A.

Plan Quality

B.

Collect Requirements

C.

Define Scope

D.

Perform Quality Control

Question 11

Job continuity would be an example of _____ in Maslow's hierarchy of needs.

Options:

A.

Self-actualization

B.

Physiological

C.

Safety

D.

Belonging

E.

Esteem

Question 12

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Page: 3 / 23
Total 625 questions