Question 69

The scope of a project can be expected to change if:

Options:

A.

The project manager must provide cost estimates without having a design concept.

B.

All of the other alternatives apply are possible based upon the situation.

C.

The project manager is assigned after the project is defined, and the cost and schedule are approved.

D.

A clear objective is not provided.

E.

Oversimplification (underestimating) of the nature of the work occurs.

Question 70

History has shown that project managers can be trained in a combination of ways.

Which method is usually preferred by most companies?

Options:

A.

None of the other alternatives apply

B.

Formal education and special course (degreed programs)

C.

Experiential learning, on-the-job

D.

Professional activities, seminars

E.

Individual readings

Question 71

The Java development of a project is outsourced to India. The project schedule is starting to slip.

What is the LEAST likely cause of the slippage?

Options:

A.

Lack of competent programmers

B.

Cultural influences

C.

Internationalization

D.

Communication

Question 72

Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:

Options:

A.

process groups.

B.

phase gates.

C.

knowledge areas.

D.

project phases.