Question 33

A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change.

What is the MOST appropriate advice for the situation?

Options:

A.

The project manager is being unreasonable and should do that kind of work herself.

B.

Remind the project manager that the benefit cost analysis for the project was done during project planning.

C.

A project manager must be able to weigh the benefits of the change versus the costs and compare them to other possible changes. The team member should do what was asked.

D.

The team member should do what was asked because this sort of information must be given to the project sponsor to make the change.

Question 34

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

Options:

A.

Perform periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards

D.

Complete the quality control checklist.

Question 35

The critical path in a schedule network is the path that:

Options:

A.

Takes the longest time to complete

B.

Allows some flexibility in scheduling a start time.

C.

Is not affected by schedule slippage

D.

Must be done before any other tasks

E.

All of the other alternatives apply.

Question 36

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.

You should calculate the forecast using which of the following methods?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS