Question 57

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Question 58

Planning activities such that predetermined resource availability pools are not exceeded is called:

Options:

A.

Manpower planning.

B.

Manpower leveling.

C.

Resource leveling.

D.

Manpower contingency planning.

E.

Resource limited planning.

Question 59

You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country.

You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival.

You know that all of the following statements are generally true except for which one?

Options:

A.

You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.

B.

You should build an atmosphere of mutual trust and cooperation.

C.

You should spend time building relationships with your prospective foreign business partners before getting down to business.

D.

You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners.

Question 60

Which of the following correctly explains the term "progressive elaboration"?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses