Question 17

The design for a new corporate office has wood wall panels with aluminum reveals. What sequence below will result in the MOST efficient installation?

Options:

A.

Installation of panels then reveals

B.

Installation of base then wood wall panels

C.

Installation of inner wall blocking then reveals

D.

Installation of reveals then inner wall blocking

Question 18

In order for a building permit to be issued, what MUST be completed?

Options:

A.

demolition phase of project

B.

submission of contract documents

C.

final inspection by a building official

D.

issuance of the certificate of occupancy

Question 19

While performing a survey of an existing elevator lobby in a sprinklered commercial building, a designer documents a dead-end corridor. How should this be corrected?

Options:

A.

coordinate with engineers to provide more sprinkler heads

B.

reconfigure the corridor to be less than 50 ft [15.2 m] in length

C.

provide a smoke detector and emergency lighting to the corridor

D.

raise the ceiling height to 10 ft [3.0 m] and include 2-hour fire-rated partitions

Question 20

What is the MINIMUM illumination level at the walking surface for a means of egress?

Options:

A.

1 footcandle [10.76 lux]

B.

2 footcandles [21.53 lux]

C.

5 footcandles [53.82 lux]

D.

9 footcandles [96.88 lux]