The NCIDQ IDPX exam tests the designer’s understanding of scope of work and professional responsibility. In this scenario, the designer’s contract explicitly excludes FF&E specification, but the designer provided general recommendations to meet code requirements. Since FF&E is outside the scope, the designer’s responsibility is limited.
Option A (Suggest that the client purchase directly from the manufacturer):This could help reduce costs, but it involves the designer taking on additional responsibility for FF&E, which is outside the contract scope. This action exceeds the designer’s role in this scenario.
Option B (Meet with the client and furniture provider to resolve the problems):While this might seem collaborative, it also involves the designer in FF&E management, which is beyond the contract scope. The designer should avoid taking on responsibilities not covered by the contract.
Option C (Research alternate furniture options to bring the budget back in line):Researching alternatives again places the designer in an FF&E role, which is not part of the contract. This action would be appropriate if FF&E were within the scope, but it is not.
Option D (Let the client and the furniture provider work out the budget problems):This is the correct choice because FF&E is explicitly outside the designer’s scope of work. The designer fulfilled their obligation by providing general recommendations to meet code requirements, and the budget issue is the client’s responsibility to resolve with the furniture provider. The designer should not take on additional FF&E responsibilities without a revised contract and compensation.
Verified Answer from Official Source:
The correct answer is verified from NCIDQ’s official study materials on professional practice and scope of work.
“If a service, such as FF&E specification, is outside the contracted scope of work, the designer should not assume responsibility for related issues unless the contract is amended to include those services.” (NCIDQ IDPX Study Guide, Professional Practice Section)
The NCIDQ IDPX Study Guide emphasizes that designers must adhere to the defined scope ofwork in their contract. Since FF&E specification is outside the scope, the designer should not take on the responsibility of resolving the budget issue, making Option D the appropriate action.
Objectives:
Understand the importance of adhering to the contracted scope of work (NCIDQ IDPX Objective: Professional Practice).
Apply professional ethics to manage client expectations (NCIDQ IDPX Objective: Contract Administration).
[References:, NCIDQ IDPX Study Guide, Professional Practice Section., National Council for Interior Design Qualification (NCIDQ), IDPX Exam Blueprint, Section on Professional Practice., ]