Supply Management Integration Questions and Answers

Question 13

Which of the following is the BEST reason to use Monte Carlo simu-lations to improve a forecast7

Options:

A.

To create a forecast that is accurate but has a wider distribution of potential outcomes

B.

To provide a single correct forecast that removes uncertainty

C.

To increase confidence in the forecast by reducing uncertainty

D.

To simulate potential outcomes and accept the resulting forecast without question

Question 14

A firm hires a new staff member in its warehousing department. As a FIRST step in the training of this employee, the warehouse manager should

Options:

A.

verify that the employee knows how to operate the warehouse equipment and tools correctly

B.

demonstrate how to package products in the correct manner, so that the employee can begin with packaging assignments

C.

explain the company's safety policy and verify that the employee understands all safety-related requirements

D.

show the employee how to separate disposable vs recyclable packaging, to ensure the employee understands environmental compliance requirements

Question 15

Which of the following requires investment recovery action’

Options:

A.

Finished goods

B.

Work-in-process

C.

Raw materials

D.

Slow-moving materials

Question 16

A supplier with a previously good performance record has recently been shipping parts with a number of flaws, making them unusable for production. The firm’s supply manager would like to resolve these problems before taking more drastic measures. Which of the following actions should the supply manager take FIRST’

Options:

A.

Explore possible root causes, including changes in the supplier's production processes

B.

Ask engineering to review tolerances on non-critical specifications and relax them if possible

C.

Test the parts at an independent laboratory and notify the supplier of the results

D.

Re-work the parts in-house and bill the supplier for any costs incurred