Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

CPSM INTE Exam Dumps

Page: 6 / 13
Total 167 questions

Supply Management Integration Questions and Answers

Question 21

A manufacturer is working to standardize high-volume, low-cost hardware components used in its assembly process. The manufacturer wants to transfer some of the risks associated with inventory carrying costs, warehousing costs, and re-stocking costs to the supplier. Which of the following will be MOST useful in accomplishing this goal?

Options:

A.

Vendor-managed inventory

B.

Reorder-point system

C.

Safety stock

D.

Kanban

Question 22

Which of the following is the PRIMARY benefit of project governance?

Options:

A.

Projects considered essential are prioritized over others already in progress.

B.

Business projects need less monitoring, which allows local managers freedom to execute their projects.

C.

Projects that are behind targets may be allowed to continue, if the cause of the delay can be resolved.

D.

Business cases and associated benefits are subject to effective scrutiny, which helps with setting project timelines.

Question 23

A manufacturing firm prepares the following materials requirement plan (MRP):

Master Production Schedule

Week123456

Item A101015152020

Relevant Information

ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory

ANone1 weekLFL50

BA2 weeks5010

CB2 weeks5010

Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7

Options:

A.

50 items immediately and 50 items in week 3

B.

20 items in week 4 and 20 items in week 5

C.

10 items in week 2 and 20 items in week 3

D.

50 items in week 2

Question 24

A supply manager learns that parts used in manufacturing are arriving scratched and must be polished before use, thereby hampering production. Sending the parts back to the supplier is not an option, as they are needed to meet increased demand. Which of the following will be MOST helpful in resolving this problem?

Options:

A.

Acceptance/rejection history

B.

Process control

C.

Corrective action plan

D.

Supplier certification

Page: 6 / 13
Total 167 questions