Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMP Exam With Confidence Using Practice Dumps

Exam Code:
PMP
Exam Name:
Project Management Professional (2024 Version)
Vendor:
Questions:
1702
Last Updated:
Mar 4, 2025
Exam Status:
Stable
PMI PMP

PMP: Project-Management-Professional Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMP (Project Management Professional (2024 Version)) exam? Download the most recent PMI PMP braindumps with answers that are 100% real. After downloading the PMI PMP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Project Management Professional (2024 Version)) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMP test is available at CertsTopics. Before purchasing it, you can also see the PMI PMP practice exam demo.

Project Management Professional (2024 Version) Questions and Answers

Question 1

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Buy Now
Question 2

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Question 3

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.