Pre-Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMI-RMP Exam With Confidence Using Practice Dumps

Exam Code:
PMI-RMP
Exam Name:
PMI Risk Management Professional (PMI-RMP) Exam
Certification:
Vendor:
Questions:
221
Last Updated:
Apr 11, 2025
Exam Status:
Stable
PMI PMI-RMP

PMI-RMP: PMI Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMI-RMP (PMI Risk Management Professional (PMI-RMP) Exam) exam? Download the most recent PMI PMI-RMP braindumps with answers that are 100% real. After downloading the PMI PMI-RMP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMI-RMP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMI-RMP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PMI Risk Management Professional (PMI-RMP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMI-RMP test is available at CertsTopics. Before purchasing it, you can also see the PMI PMI-RMP practice exam demo.

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

Options:

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

Buy Now
Question 2

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.

Contact the risk managers of the other projects and inform them

B.

Include an escalation process in the risk management plan

C.

Take note of the extensive impact of these risks in the risk register

D.

Address the unique characteristics of these risks on a case-by-case basis

Question 3

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity