Month End Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMI-100 Exam With Confidence Using Practice Dumps

Exam Code:
PMI-100
Exam Name:
Certified Associate in Project Management (CAPM)
Certification:
Vendor:
Questions:
704
Last Updated:
Jan 30, 2025
Exam Status:
Stable
PMI PMI-100

PMI-100: CAPM Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMI-100 (Certified Associate in Project Management (CAPM)) exam? Download the most recent PMI PMI-100 braindumps with answers that are 100% real. After downloading the PMI PMI-100 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMI-100 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMI-100 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Certified Associate in Project Management (CAPM)) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMI-100 test is available at CertsTopics. Before purchasing it, you can also see the PMI PMI-100 practice exam demo.

Certified Associate in Project Management (CAPM) Questions and Answers

Question 1

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Buy Now
Question 2

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Question 3

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.