New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

BICSI RCDDv14.1 Online Access

Page: 2 / 12
Total 320 questions

BICSI Registered Communications Distribution Designer - RCDDv14.1 Questions and Answers

Question 5

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

Options:

A.

If This Then That (IFTT)

B.

Gantt Chart

C.

Work Breakdown Structure (WBS)

D.

Critical Path Method (CPM)

E.

Program Evaluation Review Technique (PERT)

Question 6

Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)

Options:

A.

Proximity to interfering sources

B.

Missing or inadequate optical connections

C.

Missing or inadequate device or cable shielding

D.

Interface designs

E.

Input signal lines

Question 7

An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review

What should the program manager do next?

Options:

A.

Assign resources lo the schedule and report the revised delivery date to the project managers

B.

Work with the project managers to refine the project schedules and deliverables to align with the program milestones

C.

Revise the project schedules to meet the program schedule and communicate to stakeholders

D.

Integrate the project schedules into the program schedule and report the revised delivery date to the project managers

Question 8

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)

Options:

A.

Test reports

B.

Shop drawings

C.

Cost summary

D.

Site survey

E.

Request for information (RFI)

Page: 2 / 12
Total 320 questions