New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

RCDDv14.1 Reviews Questions

Page: 8 / 12
Total 320 questions

BICSI Registered Communications Distribution Designer - RCDDv14.1 Questions and Answers

Question 29

Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)

Options:

A.

Electrical metallic tubing (EMT)

B.

Aluminum metal conduit (AMC)

C.

Flexible metal conduit (FMC)

D.

Intermediate metal conduit (IMC)

E.

Rigid metal conduit (RMC)

Question 30

What is the PRIMARY reason for considering a physical ting topology for connecting outlying buildings?

Options:

A.

It is the most cost effective design ten a campus network.

B.

It provides a redundant cable path for disaster recovery.

C.

It is the most compelling design for any network requirement.

D.

It is an easier physical design to install.

Question 31

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program

As a result, the program manager must do which of the following'?

Options:

A.

Utilize team members that are currently available, even though they do not have the expertise needed.

B.

Assign the tasks on the critical path to the resources available to adhere to the project schedule

C.

Delay the start of the program until the assigned resources are available

D.

Apply resource leveling considering the constraints of time, budget, and quality

Question 32

A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?

Options:

A.

Milestone dates, budget, and staff details that support it

B.

Assumptions incorporated into the benefits management plan

C.

Process within the organization that will be needed to deliver the product

D.

Key decision makers or stakeholders in the program and their expectations and interests

Page: 8 / 12
Total 320 questions