Question 77

What oversight should the information security team have in the change management process for application security?

Options:

A.

Information security should be informed of changes to applications only

B.

Development team should tell the information security team about any application security flaws

C.

Information security should be aware of any significant application security changes and work with developer to test for vulnerabilities before changes are deployed in production

D.

Information security should be aware of all application changes and work with developers before changes are deployed in production

Question 78

Your incident response plan should include which of the following?

Options:

A.

Procedures for litigation

B.

Procedures for reclamation

C.

Procedures for classification

D.

Procedures for charge-back

Question 79

When is an application security development project complete?

Options:

A.

When the application is retired.

B.

When the application turned over to production.

C.

When the application reaches the maintenance phase.

D.

After one year.

Question 80

Knowing the potential financial loss an organization is willing to suffer if a system fails is a determination of which of the following?

Options:

A.

Cost benefit

B.

Risk appetite

C.

Business continuity

D.

Likelihood of impact