Easter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMI-RMP Exam With Confidence Using Practice Dumps

Exam Code:
PMI-RMP
Exam Name:
PMI Risk Management Professional (PMI-RMP) Exam
Certification:
Vendor:
Questions:
221
Last Updated:
Apr 19, 2025
Exam Status:
Stable
PMI PMI-RMP

PMI-RMP: PMI Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PMI PMI-RMP (PMI Risk Management Professional (PMI-RMP) Exam) exam? Download the most recent PMI PMI-RMP braindumps with answers that are 100% real. After downloading the PMI PMI-RMP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PMI PMI-RMP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PMI PMI-RMP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PMI Risk Management Professional (PMI-RMP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PMI-RMP test is available at CertsTopics. Before purchasing it, you can also see the PMI PMI-RMP practice exam demo.

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Options:

A.

Review assumptions and constraints around risks.

B.

Develop the risk response plans for identified risks.

C.

Determine the likelihood and impact of the risks.

D.

Apply an iterative approach to risk identification.

Buy Now
Question 2

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Question 3

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.