Question 37

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

Options:

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Question 38

Which of the following best describes a rollback plan?

Options:

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Question 39

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Question 40

A project's QA team needs to validate functionality in a timely and cost-effective way to ensure good coverage every time a new change is integrated. Which of the following test should the team execute?

Options:

A.

Sanity

B.

Manual

C.

Automated

D.

Regression