Question 29

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Question 30

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Question 31

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

Options:

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Question 32

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.