Question 29

Which of the following would help a project manager identify that project goals have been reached?

Options:

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Question 30

Which of the following demonstrates awareness of regulations and standards when conducting a project?

Options:

A.

Establishing a measurement system for the team members' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Question 31

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Part 2:

Options:

Question 32

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.