Question 57

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Question 58

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

Options:

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Question 59

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options:

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

Question 60

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

Options:

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.