New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI-100 Reviews Questions

Page: 9 / 26
Total 704 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 33

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Question 34

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Question 35

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Question 36

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Page: 9 / 26
Total 704 questions