Certified Associate in Project Management (CAPM) Questions and Answers

Question 57

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

Options:

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Question 58

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Question 59

Which Manage Communications tool or technique focuses on identifying and managing barriers?

Options:

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Question 60

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action