New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI CAPM PMI-100 New Questions

Page: 25 / 26
Total 704 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 97

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Question 98

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Question 99

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Question 100

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Page: 25 / 26
Total 704 questions