New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Exactprep PMI-100 Questions

Page: 24 / 26
Total 704 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 93

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

Options:

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Question 94

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Question 95

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

Options:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Question 96

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Page: 24 / 26
Total 704 questions