New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Pass LEED-Green-Associate Exam Guide

LEED Green Associate Exam (LEED GA) Questions and Answers

Question 17

What is the process that is performed on existing buildings to identify and recognize system improvements that make the building more suitable for current use?

Options:

A.

Energy modeling

B.

Retrocommissioning

C.

Life-cycle assessment

D.

Fundamental Commissioning (Cx)

Question 18

The LEED Pilot credit library plays an important role in the continuous evolution of LEED by

Options:

A.

developing new credits for U.S. projects only

B.

achieving the next threshold for exemplary performance

C.

limiting the number of times that a credit category appears in the rating system

D.

providing U.S. Green Building Council (USGBC) with feedback on achievability of proposed credits

Question 19

In the context of a LEED project, the charrette is a

Options:

A.

set of preliminary design specifications submitted by project team members

B.

forum at which the final schematic of the project is presented to the community

C.

procedure through which experts are selected to participate on the project team

D.

meeting of stakeholders, project team members and others to establish project objectives

Question 20

Which of the following facilitates the recharging of aquifers?

Options:

A.

Asphalt road

B.

Pervious paving

C.

Impervious paving

D.

Concrete parking lot