Managing Performance Questions and Answers

Question 29

A project manager is calculating the budget cost of a single project task called "Server Configuration".

 

This task is estimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.

One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.

 

Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.

 

Give your answer as a whole number.

 

The total cost is $    .

Options:

Question 30

Various methods of communication are available, including face to face, by telephone or online.

 

Which THREE of the following interactions are best conducted face to face?

Options:

A.

Discussion of the proposed strategy for the company between its senior managers.

B.

Booking hotel accommodation.

C.

Conducting a training session on how to administer life-saving first aid.

D.

Purchasing a well known brand of printer cartridges.

E.

Arranging the details of a joint venture with a new partner from a foreign country.

Question 31

A Company achieves its competitive advantage by adopting a positioning view to strategy setting.

 

Which TWO of the technical models below are most suited to this approach?

Options:

A.

Michael Porter's Value Chain.

B.

PESTEL analysis.

C.

Michael Porter's Five Forces model.

D.

Resource Audit.

Page: 8 / 8