Question 17

Which of the following actions is typically associated with delegated design in large-scale construction projects?

Options:

A.

Transferring total project management to a single contractor

B.

Outsourcing construction activities

C.

Centralizing design tasks with the lead architect

D.

Assigning specific design responsibilities to specialty firms

Question 18

How should a Quality Manager best utilize customer complaint logs to capture both positive and negative feedback effectively?

Options:

A.

Use complaint logs that are focused on negative aspects to identify areas for improvement.

B.

Incorporate options in complaint logs for both criticisms and commendations.

C.

Use complaint logs for legal documentation, not for feedback.

D.

Restrict access to complaint logs to senior management.

Question 19

Which of the following is a critical consideration when evaluating the impact of a project's delivery method on design phase planning?

Options:

A.

The delivery method integrates quality objectives into the design plan

B.

The delivery method aligns with the project's financial objectives

C.

The geographical location is relevant to the selected delivery method

D.

The delivery method allows for flexible scheduling and resource allocation

Question 20

Which of the following best describes why securing all essential permits before project commencement is important?

Options:

A.

It ensures all materials are delivered on schedule

B.

It guarantees the availability of construction equipment

C.

It prevents legal and regulatory complications during construction

D.

It confirms the project budget allocation