Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Complete CCQM ASQ Materials

Page: 10 / 12
Total 165 questions

Certified Construction Quality Manager Questions and Answers

Question 37

When assessing the process of communicating lessons learned, what aspect should be evaluated to ensure it benefits future projects?

Options:

A.

The clarity and accessibility of the documented lessons for all project team members

B.

The graphical presentation of the lessons in reports to properly illustrate key points

C.

The number of lessons learned sessions conducted on similar topics

D.

The application of documented lessons in future project planning and implementation

Question 38

Which of the following factors is the most critical for evaluating the completeness and readiness of quality deliverables for project turnover?

Options:

A.

The deliverables have been reviewed by the entire quality team.

B.

The deliverables have been endorsed by all external consultants.

C.

The deliverables meet the project's internal quality guidelines and review criteria.

D.

The deliverables meet all compliance and regulatory requirements for the project.

Question 39

When designing a protocol for overseeing pre-activity meetings, such as quality kick-offs, that effectively engage all relevant stakeholders (e.g., subcontractors, suppliers, project management teams), what aspects are essential for this protocol to ensure all parties are actively involved and their input is effectively integrated into the project planning?

Options:

A.

Oversee meetings that primarily provide updates from the project manager without soliciting input from other stakeholders.

B.

Conduct meetings informally to encourage a relaxed atmosphere and spontaneous discussion to identify potential risks and to resolve issues prior to the pre-activity meeting, which will allow a shorter meeting.

C.

Structure meetings to include input from each group and implement follow-up actions.

D.

Limit stakeholder participation to only major contractors to streamline the meetings.

Question 40

Which of the following is the most effective way for a construction quality manager to review an 'action' submittal to ensure alignment with the project's quality plan?

Options:

A.

Approve the submittal based on cost-effectiveness.

B.

Prioritize speed of approval to keep the project on schedule.

C.

Verify the submittal meets all specified standards and requirements.

D.

Involve subcontractors in the review process with regular oversight.

Page: 10 / 12
Total 165 questions